BBV HS2 MWCC North - SL5s Kerb Laying Package
Details
- Supplier(s)
- P&M pavers (lincoln)ltd
- Value
- £243,047
- Duration
- 2 years
- Topic
- Kerbstones
- Published
- 14 November 2022
- Source
- uk:contracts_finder
Tender description
Balfour Beatty VINCI (BBV) have been awarded HS2 main works civils contracts, lots N1 and N2 under an Early Contractor Involvement contract (ECI). We are currently in stage one of a two stage process. We are looking to engage with a local and competent supply chain whom provide kerb laying capability's. The works to take place will involve the subcontractor's in house ability to install all Kerbs, Kerbdrains, footpath edgings. Approximately 3500m Half Batter Kerbs, 6700m Splay Kerbs, 2400m Marshall Beany Kerb Drain, 3300m Flat Top Footpath Edging Pin Kerb and all associated Quadrants / Drop Kerbs / Bullnose Kerbs etc. Full details and specifications will be provided to the successfully shortlisted suppliers. Suppliers should be aware of the scale of this project and should assess their internal capabilities to be able to carry out the intended scope of works, prior to completing this expression of interest (EOI).
Timeline
- Completed: Award date31 January 2022
- Completed: Award published14 November 2022Current notice
- Completed: Contract expiry date31 January 2024
About the buyer
HS2 Ltd is a non-departmental public body sponsored by the Department for Transport, and buys as a central government agency building Britain's high-speed railway between London and Birmingham. Contracts above the public procurement threshold are advertised on Find a Tender, and smaller awards appear on Contracts Finder. Framework agreements cover major packages, such as the lifts and escalators for Phase One stations. Four tier-one joint-venture contractors, including EKFB and Align JV, deliver the main civils work. Those contractors procure their own tier-two subcontractors, who source further down the chain. Live subcontract opportunities are advertised through the CompeteFor portal.
Procurement spend from central entities makes up 66% of overall UK public spend.
Over the past 5 years, most of HS2's contract awards have been in construction work, metals and mining products and transport equipment.
Relevant CPV codes
- 44912400 · Kerbstones
- 45233222 · Paving and asphalting works
- 45432112 · Laying of paving
Decision makers
Connect with the people behind this procurement.
| Contact name | Job title | Phone number | Work email |
|---|---|---|---|
| Head of Procurement | +44 •••• •••••• | ••••••••@high-speed-two-hs2-ltd.gov | |
| Commercial Director | +44 •••• •••••• | ••••••••@high-speed-two-hs2-ltd.gov | |
| Procurement Manager | +44 •••• •••••• | ••••••••@high-speed-two-hs2-ltd.gov | |
| Category Lead | +44 •••• •••••• | ••••••••@high-speed-two-hs2-ltd.gov | |
| Senior Buyer | +44 •••• •••••• | ••••••••@high-speed-two-hs2-ltd.gov | |
| Contracts Manager | +44 •••• •••••• | ••••••••@high-speed-two-hs2-ltd.gov |
21 similar open tenders
See more open tenders related to BBV HS2 MWCC North - SL5s Kerb Laying Package.
- Open tender
TD2340 - Framework for Highways Services
- Open tender
St Ives Crescent SuDS
- Open tender
Maintenance and Response 2 Framework
- Open tender
YPO - 000881 Ground Maintenance Services
Related topics
Topics related to BBV HS2 MWCC North - SL5s Kerb Laying Package, ranked by notice volume.
- 14,527£1.1tn
Related buyers
Buyers similar to High Speed Two (HS2) Ltd.
- 3,054£1.8bn
- 1,200£14.2bn
- 803£8.9bn
- 551£22.8bn
- 485£3.8bn
- 427£24.7m
- 376£414.1m
- 300£335.8m
- 293£10.2bn
- 272£693.5m
Win more public sector contracts
Track every UK and Ireland tender in one place — set up alerts, find decision-makers, and never miss an opportunity.