Stotles logo
Closed

River Thames Scheme (RTS) Construction Partner

Published

Value

500,000,000 GBP

Description

The River Thames between Egham and Teddington has the largest area of undefended, developed floodplain in England. Over 10,000 homes and businesses within the area are at risk from flooding.<br/>Major flooding in this area would cause severe disruption to the local and regional road network. It would suspend several major drinking water abstractions supplying the South East and threaten up to 20 local electricity sub-stations.<br/><br/>The River Thames Scheme (“RTS”) is being delivered in partnership between the Environment Agency and Surrey County Council and will reduce the risk of flooding to homes, businesses and critical infrastructure (roads, sewerage network, and power supplies) between Egham and Teddington. <br/><br/>The scheme consists of:<br/><br/>• Construction of 8 km of new flood channel built in two sections;<br/>• Improving the flow capacity at Sunbury, Molesey and Teddington weirs;<br/>• Improving the flow capacity downstream of the Desborough Cut channel;<br/>• Building community resilience through flood planning and improved emergency planning;<br/>• Creating new green open spaces and habitat creation areas;<br/>• Providing a new sustainable travel route.<br/><br/>RTS will reduce flood risk to people living and working near the Thames, enhance the resilience of nationally important infrastructure, contribute to a vibrant local economy and maximise the social and environmental value of the river. Lot 1: The Environment Agency (EA) and Surrey County Council (SCC) are seeking to appoint a Construction Partner to deliver the River Thames Scheme. The EA shall be the sole contracting authority with the contract providing SCC with access rights by way of a collateral warranty.<br/><br/>The main works include design and construction of the 8km flood channel built in two channel sections:<br/><br/>• Egham Hythe to Chertsey;<br/>• Laleham to Shepperton.<br/><br/>and will include design and construction of the following:<br/><br/>• Increasing the flow capacity of Sunbury, Molesey and Teddington weirs;<br/>• Increasing the capacity downstream of the Desborough Cut;<br/>• Highways bridges, roads and footbridges on private and public land, work to M3 motorway assets and utility service diversions, including the Southampton to London pipeline;<br/>• Landscaping works including creation of areas for community use post construction and areas of habitat created to mitigate impacts during construction;<br/>• Active travel routes to encourage cycling and other forms of non-motorised travel;<br/>• Earthworks including excavation, storage, treatment, placement and disposal of approx. 1 million mᶾ of material including landfill waste, topsoil, alluvium and gravels - this represents a significant proportion of the overall construction costs;<br/>• New operational assets to ensure the channel can be operated and maintained by a dedicated team once in service.<br/><br/>The contract shall be awarded in two stages as described below:<br/><br/>Stage One – Early Contractor Involvement phase - Design Development and Construction Planning: <br/><br/>• Mobilisation of the design team and undertaking full detailed design; <br/>• Carry out surveys as appropriate to inform design and consenting requirements; <br/>• Conduct sub-contractor procurement and agree pricing based on detailed design, carry out two stage appointments if necessary; <br/>• Work progressively on the pricing proposals for Stage Two Works with reference to the Pricing Information, programme and Construction Partner’s design for the Full Business Case (FBC); <br/>• Plan/apply for permits & licences in accordance with the consenting strategy; <br/>• Engage specialist suppliers through its design process; <br/>• Critically review the apportionment of risk and adopt a methodology of reducing the Client’s risk in key areas; <br/>• Collaborative development of KPIs that are to be adopted during Stage Two; <br/>• Provide proposals for value engineering and optimisation where possible; <br/>• Deliver project ambitions for carbon emissions and sustainability goals; <br/>• Plan to prepare and commence works on site as soon as DCO is granted and FBC is approved; <br/>• Take ownership of the existing relationship and negotiations with utility providers and undertake any necessary service diversion works necessary prior to Stage Two subject to funding approval; <br/>• Any potential enabling works such as site clearance, site possession and security; <br/>• Work collaboratively with the Client’s design team for assurance on design activities. <br/><br/>Stage Two – Construction works:<br/><br/>• Site mobilisation; <br/>• Early works not completed in Stage One such as site clearance, site possession and security; <br/>• Construction phase; <br/>• Maintenance of the planted landscape elements; <br/>• Reporting, health & safety file, O&M and handover at completion. <br/><br/>The Stage One contract shall be awarded to the successful bidder from this procurement process. Award of the Stage Two contract shall be subject to a number of success criteria that shall be defined in the Invitation to Tender (ITT). The intention is to award the Stage Two contract to the successful bidder from this procurement process but, in the event that the success criteria are not met, the Contracting Authority reserves the right to award the Stage Two contract to a different contractor.<br/><br/>The Authority estimates that delivery of RTS in its entirety may cost in the region of £300m - £375m. This estimate includes all pre-construction and construction activities that the Authority may require the successful contractor to undertake but does not include any other compensation events or permissible price increases during the term and therefore the Authority has estimated the total maximum value of the contract in the Contract Notice to be higher than this at £500,000,000 to provide some flexibility. <br/><br/>The construction programme for the successful completion of the works is expected to be a period of approximately 7.5 years (91 months) though this does not take account of as yet unforeseen requirements of the DCO approval, any extensions of time permissible by the Contract, the defects period, or any maintenance provision. The contract shall continue until the completion of the works and all of the subsequent related contractual obligations have been fulfilled unless terminated earlier in accordance with its terms.<br/><br/>The Competitive Procedure with Negotiation is the selected procurement procedure for the RTS Construction Partner requirement. Two stages of shortlisting shall be utilised as follows:<br/><br/>• The Selection Questionnaire (SQ) shall apply the selection criteria to shortlist Candidates to a minimum of 4 and maximum of 6 for ITT. <br/><br/>• Initial tender responses shall be evaluated in accordance with the ITT evaluation model and a maximum of 3 taken forward to the negotiation stage. <br/><br/>The shortlisted bidders will be invited to participate in negotiations. The negotiations could cover any aspect of the tender, from the quality of the solution to contractual clauses, costs, innovation incentives, or ways in which solutions will be implemented excluding the defined minimum requirements which are not subject to negotiation. <br/><br/>The form of contract shall be an NEC4 Engineering & Construction Contract (ECC) utilising the Option C (Target Cost Incentive Model with Activity Schedule) pricing option for both Stage One and Stage Two. The share ranges for the Stage One contract shall be set to zero but appropriate share ranges shall be set for the Stage Two contract.

Timeline

Publish date

4 months ago

Close date

2 months ago

Buyer information

Environment Agency

Contact:
Jon Mannering
Email:
jon.mannering@environment-agency.gov.uk

Explore contracts and tenders relating to Environment Agency

Go to buyer profile
To save this opportunity, sign up to Stotles for free.
Save in app
  • Looking glass on top of a file iconTender tracking

    Access a feed of government opportunities tailored to you, in one view. Receive email alerts and integrate with your CRM to stay up-to-date.

  • ID card iconProactive prospecting

    Get ahead of competitors by reaching out to key decision-makers within buying organisations directly.

  • Open folder icon360° account briefings

    Create in-depth briefings on buyer organisations based on their historical & upcoming procurement activity.

  • Teamwork iconCollaboration tools

    Streamline sales workflows with team collaboration and communication features, and integrate with your favourite sales tools.

Stop chasing tenders, start getting ahead.

Create your free feed

Explore similar tenders and contracts

Browse open tenders, recent contract awards and upcoming contract expiries that match similar CPV codes.

Explore other contracts published by Environment Agency

Explore more open tenders, recent contract awards and upcoming contract expiries published by Environment Agency.

Explore more suppliers to Environment Agency

Sign up